One of the most advanced biorefineries is being built in Saxony-Anhalt to produce sustainable chemicals. The technical requirements and environmental ambitions of the project demand precise and meticulous execution of the installation work, with cable laying playing a particularly crucial role.
The project, which began in July 2023, presents our team with the challenge of laying over 800 kilometres of cable. More than 30 employees are involved in this extensive project, which stands out for its significance to the chemical industry and, in particular, to the emerging bioeconomy. This project underscores Bähr Anlagenbau’s ability to effectively manage and execute complex, large-scale installation contracts in the chemical industry. It demonstrates our commitment to supporting innovative and sustainable industrial solutions that offer both economic and environmental benefits.
30+
Staff on duty
18
months of construction
800+
KM Cable
Project data
- Industry
- Chemie
- Construction location
- Germany
- Contruction period
- 18 months
- Contributors
- 30+
Scope of delivery & service