Germany
Cable connection, Cable laying, Cable route planning and construction, Project management, Switchgear installation
The team at Bähr Anlagenbau has successfully completed the electrical installation work on the polyamide plant in North Rhine-Westphalia. Our Bähr team was responsible for the electrical installation, which involved laying over 300 kilometres of cable and installing 90 control cabinets, as well as carrying out cable pulling and connection work and erecting substructures. The team, comprising up to 45 skilled workers, mastered the technical and safety-related challenges of the chemical industry with flying colours. The successful completion of the project underlines Bähr Anlagenbau’s expertise and reliability in the field of industrial installation and consolidates our position as a preferred partner in the chemical industry.
45
Staff on duty
18
months of construction
300+
KM Cable
90
Control cabinets
Project data
- Industry
- Chemie
- Construction location
- Germany
- Contruction period
- 18 months
- Contributors
- 45
Scope of delivery & service
Electrical installation